August 3, 2022 9.39 am This story is over 19 months old

Latest traffic restrictions due to Grantham Southern Relief Road works

Phase Three works continuing ahead

What we achieved in July

Phase Two

  • Resurfacing works to northbound A1 Lane 2
  • Testing and commissioning of northbound and southbound streetlights on the A1

Phase Three

  • West side of site – pier 1 bases concreted / pier 2 reinforcement fixed / pier 3 cofferdam excavated / embankment construction materials stockpiled
  • East side of site – continued drainage, ducting and kerbing works at Somerby Hill roundabout / soakaways dug between Whalebone Lane and development / continued with rock processing operations

What’s happening in August

Phase Three

  • West side of site – pier 2 bases concreted / pier 3 bases reinforcement fixed and concreted
  • East side of side – complete works at Somerby Hill roundabout / install filter drains and road box between Whalebone Lane and development / begin next set of ground investigation works

Current/ongoing traffic restrictions and closures

  • Ongoing lane closures on the B1174 roundabout until the end of the scheme
  • Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout

Upcoming traffic restrictions and closures

  • N/A