April 7, 2017 9.25 am This story is over 83 months old

Extra dates added to Yarborough Road works

A set of additional dates have been added to ongoing road restrictions on Yarborough Road in Lincoln. As reported previously, the northbound lane of Yarborough Road was subject to a number of daytime lane closures to allow for a 66 week construction project at St. Faiths & St Martins Junior School on Hampton Street. Contractors Kier…

A set of additional dates have been added to ongoing road restrictions on Yarborough Road in Lincoln.

As reported previously, the northbound lane of Yarborough Road was subject to a number of daytime lane closures to allow for a 66 week construction project at St. Faiths & St Martins Junior School on Hampton Street.

Contractors Kier Construction have said that due to a re-sequencing of the works, the next planned lane closures are from April 10 to 13 and April 24 to 28 between the hours of 9am and 3pm, Monday to Friday.

All other previously outlined dates will stay the same:

  • Monday. April 10 – Friday, April 14
  • Monday. April 24 – Friday, April 28
  • Monday, May 8 – Friday, May 12
  • Monday, May 22 – Friday, May 26
  • Monday, May 29 – Friday, June 2

A spokesperson from contractor Kier Construction said: “During these times an additional crossing point will be installed to assist pedestrians around the works and vehicle access in both directions will be maintained via two way temporary signals. We apologise in advance for any inconvenience caused.”